01 - LANCASTER TUNNEL

Location: Birmingham. England
Contract Value: £20,000
Start Date: 6th March 2006
Completion: 21st March 2006
Scope: Supply test and commission.
Pictured: Birmingham Tunnel
02 - LUNDBY TUNNEL

Location: Stockholm
Contract Value: £200,000
Start Date: January 2006
Completion: February 2006
Scope: Supply test and commission.
Pictured: Stockholm
03 - AUTOM PARKING TOWER

Location: Taipei Peoples Republic of China
Contract Value:
Start Date: 1999
Completion: 1999
Scope: To protect an underground car park in a tower block.
Pictured: Fire Detection in the Underground Parking
04 - PPL POWER STATION CABLE TRAYS

Location: Alivori, Greece
Contract Value:
Date: 1999
Scope: To protect cable trays throughout a power station.
Pictured: Cable Trays
05- BASF BECT CONVEYOR SYSTEM

Location: Ludwiclshafen, Germany
Contract Value:
Date: 1995
Scope: To protect a belt conveyor.
Pictured: Belt Conveyors in the Power Station
06- WALDAU - WERNHALDE RAIL AND SUBWAY TUNNELS AND MARSHALLING TUNNELS

Location: Stuttgart Germany
Contract Value:
Date: 1998
Scope: To protect a repair shed.
Pictured: Stutggart
07 - LUZERN COLD STORAGE DEPOT

Location: Luzern, Switzerland
Contract Value:
Start Date: 2004
Completion: 11
Scope: To protect a cold storage area utalising
differnetial minus temperatures.
Pictured: Lake Luzern
   
 
PRODUCT QUICKFIND TECH SPECS APPROVALS


click CLICK HERE

click View Certificates CLICK HERE
 
HOME I OUR PHILOSOPHY I BROCHURE I CONTACT I LOCATION I SITE MAP I EXTRANET I DISCLAIMER
POWER GENERATION I FIREPROOF CABLES I HEAT DETECTION I DIGITAL CABLES I BESPOKE CABLES I OTHER CABLES